The AG in her
report was quite correct that the project deliveries will have been delayed three years from the original intended timeline; a trickle-down effect of the contract with Boeing being signed three years later (2009 vice 2006) than originally foreseen.
(see timelines
here)
The original timelines of the MHLH project advance contract award notice (ACAN) in early 2006 stated a 2010 delivery of the first aircraft, based on a delivery 36 months after contract award originally anticipated to be signed in mid 2007. The contract was actually signed in July of 2009. The first aircraft will be delivered this summer, still 36 months after contract award. The aircraft (and a sister ship) will immediately enter a year-long flight test program, and the first operational, Canadianized aircraft will be delivered in the summer of 2013, per the AG's timeline noted above.
The AG's report contains no mention of D-model rebuilds delaying the program, this is an inaccuracy reported by Mr. Fisher. Ms. Fraser and her staff were quite aware of the differences between the interim six D-model Chinooks being procured based on the Manley Report recommendations, and of the long-term new-build aircraft based on the F-model Chinook of the MHLH project.
Mr. Fisher fell prey, as did many other reporters, to a hasty analysis of various planning estimates that could lead the uninitiated (or those who might deliberately want to add drama with comparatives) to the incorrect conclusion that acquisition costs more than doubled. This is not accurate since the 2006 figure in Treasury Board documents included ONLY the
capital acquisition costs. The 2006 estimate for capital acquisition costs was $2.022B. The 2009 budgeted and contracted amount was $2.313B, a 14% increase. These amounts are clearly presented in the AG's report at
Exhibit 6.6 - Estimated costs for MHLH presented in Treasury Board submissions. (figures below are copied from Exhibit 6.6)
Preliminary Project Approval Effective Project Approval
June 2006 November 2009
(In millions of Canadian dollars)*
Capital costs
Medium- to heavy-lift helicopters 1,025 1,245
Initial set-up (engineering, spares, training) 457 496
Project management 48 122
Contingency and escalation/inflation 430 232
Infrastructure 62 218
Total capital costs
2,022 2,313
Personnel, operating, and maintenance costs
Contracted in-service support
not included 2,573
National Defence personnel not included not included
National Defence operating costs not included not included
Total personnel, operating, and maintenance costs — 2,573
Total costs 2,022 4,886 ( <-the source of the 'more than doubled' phrase)
* Figures have been rounded.
Source: Key approval documents—unaudited figures
In 2006, the specific contracted in-service support costs had not been formalized yet, and could not be presented, as those costings were still being developed by the project team and Boeing.
Could a reporter say "the costs more than doubled" in an apples to oranges comparison? Yes, they could (and did). But if they were to do so, one would expect a professional also to note to the reader that the earlier costs did not include the maintenance costs to maintain the Chinooks for 20 years. To my knowledge, not a single reporter has done so.
What is often missed (ignored?) by many is that DND was up front with its cost estimates from the very beginning, estimating a total project cost that was in fact $2B higher than the eventual Cabinet-authorized budget. Ms. Fraser and her team identified it in the report's paragraph 6.67:
6.67 Early in the project, National Defence recognized in principle the elements needed, in addition to the helicopters, to provide full operating capability, such as personnel, training, infrastructure, operations, and long-term in-service support. In seeking Cabinet approval in principle for the acquisition in June 2006, National Defence had estimated the total long-term project costs to be $6.9 billion.
The thing is, the media doesn't like to report "DND TO DELIVER HELICOPTERS FOR 2 BILLION LESS THAN THEY ASKED FOR."
Now, to be totally accurate with an analysis of the total project costing, one can't say that DND saved $2 billion -- one must also ask themselves what DND's Personnel and Operating costs would be during the in-service period of the Chinook - remember, they were also 'not included' in the original '
preliminary project approval' document. DND has lots of room for its operating costs to end up being lower than its original estimates -- $2 billion (the difference between the $6.9B estimate and the $4.9B acquisition and maintenance costs) over 20 years is $100 million annually for salaries and fuel for the Chinook fleet.
Rough order-of-magnitude costing would look at say, 500 personnel directly or indirectly involved in Chinook operations. I don't know how much a DND average per person cost is, but let's use a conservative average of $100,000 to include salary, pension, administration, HR cots, etc... so that's 500 x $100,000 = $50 million annually for the "P" of P, O & M. Now how about the Operations? Let's say the fleet will fly a per aircraft yearly flying rate (YFR) similar to the Griffons. Prorated for the 15 Chinooks, that would be between 5000 and 7000 hours annually. Let's be conservative, and take the larger number, so 7000 hours flown, multiplied by 1,400 L/hr burned by a Chinook, multiplied by a conservative $1.50/L for kerosene = $14,700,000 annually. So...we add $50 million for people and $14.7 million for direct operating costs, add on say $5 million a year to run the squadron facility...that puts us at $69.7 million annually, compared to DND's original estimate of $100 million annually for P&O costs.
Thus, over 20 years, it's reasonable to estimate that the pers and operating costs would be 20 x 69.7M = $1.394 billion.
Add that figure to the $4.886 billion figure for capital acquisition and in-service support costs and we have:
$4.886B + $1.394B = $6.280B
So, in 2005, DND estimated the Chinook would cost $6.9B over a 20-year service life. Using approved budgets and some rough estimation, it is entirely reasonable that DND would actually spend $6.3B. That actually looks like a projected savings over the Chinooks's service life of $600 million from the original estimate...or $30 million / year underspent.
My :2c:
Regards
G2G